Work to the lift station and sewer system on Old Highway 24 in Carrollton continues.  Click to hear KMZU’s Kristie Cross speak with Wastewater Department Superintendent Randy Johnson:

Audio clip: Adobe Flash Player (version 9 or above) is required to play this audio clip. Download the latest version here. You also need to have JavaScript enabled in your browser.

They are doing an upgrade to the lift station and some upgrades on the sewer system. Old Highway 24 remains closed while it is underway.

“I appreciate all the people staying away from the area, because the safety feature’s why we have it shut down.  And I know the guys working on that really appreciate it,” said Johnson.

Depending on weather, the project is scheduled to be completed in July.

“They had some setbacks with the rain and everything, but they’re basically on schedule,” said Johnson, “They’re waiting on a time frame on submittals, and the process will be starting up after everything dries up again.”

The $5.4 million project is funded by a bond issue passed by voters.